South High-Rise

South High Rise renovation and expansion

This project involves extensive renovations to Siebert, Stradley, Park, Smith, and Steeb Halls.  While undergoing one of the largest renovations in Student Life, these building will be completely updated and add two bold additions to the existing buildings which will create a total capacity of 2,483 beds. The additions will connect Stradley/Park Halls and Smith/Steeb Halls, thereby creating two H buildings from four.  This project will strive to attain LEED silver or better certification.  We are also going to use the most efficient Heating and Cooling systems available and 40 % of this will come from Geothermal systems. This system will provide the capacity for additional air conditioning in the future for the other south residential district buildings

We are creating Central Ohio Jobs as well as using as much as possible Ohio materials. 

For general questions about this project, please send e-mail to Cihangir Calis, OSU, Project Manager. 

Schedule:

There are Two General phases to the South High-Rise Project:

Phase I) Park-Stradley reopened in August 2012 and

Phase II) Steeb-Smith and Siebert reopening in August of 2013. 

Within these two general phases, are several stages:

  • Utilities Relocation: March 2010 to October 2010
  • Flooring Removal: Summers of 2010-2013
  • Chiller Bunker (between Park and Stradley): August 2010 to March 2010
  • Geothermal Well Fields and System: November 2010 to January 2012
  • Central HVAC Plant: December 2010 to May 2012
  • Construction and Renovation (Main Building) June 2011 to July 2013